on 06-29-2015 10:19 AM
Hi, Colleagues
Who knows how make report in report for cost centers and projects?
The problem: When make a Library I choose a component ID. If I choose CO as component ID, it works with cost centers or orders but it does not work with projects. If I choose PS as component ID, it works with projects but it does not work with cost centers, orders. I want to make report which collected a cost center cost and project costs.
I think it possible because I create library with table CCSS and table CCSS have all requirement information.
Hi,
Why don't you create a library based on CCSS and select OBJNR as characteristic? Doesn't it work this way?
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, I can make range numbers for orders, cost centers. Because OBJNR of orders, cost centers are based on id of orders, cost centers. For example, orders ids have range 30000- 39999, and OBJNR for order have a range OR000030000 - OR000039999. But it is not suitable for projects. OBJNR for projects created automatically and OBJNR are not based on ids of projects.
I have to group orders, cost centers, projects in one report. If I could make a range numbers for orders, cost centers and projects in one report, it was possibale. But it is not worked I wrote about early.