on 06-30-2015 6:48 AM
Dear Experts,
Greetings for the Day!!!!!
In which transaction code we can get the commitment information of project with "Back Dates" like if any project runs more than one year then, commitment information of project will be last year with specific period.
regards
Jk
Hi JK,
have you tried CJI5 for commitment values for projects.. Give a date range for which you want to see the commitments..
Regards
Sammar