on 06-30-2015 12:58 PM
Hello ,
If we take the example given in sap's page :
You want to check the washers of a pump every time 50,000 liters of water have flowed through it. The system calculates the planned date by which 50,000 liters must have flowed through the pump.
So how does the counter to calculate the planned date ?
Thanks.
The Key things in Counter Based Plan are
- e.g. Initial reading is 100 Ltr
- The pump in question discharges 1500 ltr of water per day; so to get to reading of (50100-100) =50000 it will take 50000/1500=33.33 Days
- System calculate plan date = Start date (Today + 33.33 Days) = 4 Aug 2015
Now the effect of posting measuring document at every week Monday-
Rgds
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just to clrify things,
If your Pump Run for 10 Hr daily (Annual estimate is 365 *10 =3650) and you plan to execute maintenance on completion of 100 Hr.
Plan start 01.07.2015 with refrence reading 10 Hrs; at 110 Hrs. System will plan date according to Annual estimate as 11.07.2015 and if you post document before this date system recalculated or if you post document after this date system would have already called Maintenance object.
This were you need to be careful in decisiding you document posting based on annual estimate.
Rgds
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.