Hi Gurus,

We are trying to develop a report to display actual and planned values of multiple WBS with respect to multiple WBS/Project number.

-We are pulling the Actual cost values from table COEP which match with CJI3 Actual values.

-We are pulling the planned cost from table COSP which gives only planned cost on network (Primary posting values). and its doesnt show planned cost for WBS (Secondary Cost).

-In COSS we are getting actual cost for WBS only.

Could you please suggest us table which can provide actual and planned cost for WBS/Network.

Thanks

SK

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Hi Suraj,

please use RPSCO table by passing Object number of WBS and Network activities.

Please refer

thanks

Sunil

former_member214736
Participant
0 Kudos

Hi Sunil,

Thanks for the promt reply, I did checked with the way you provided but unfortunately it is not tallying with the report S_ALR_87013542.

Thanks

SK

sunil_yadav2
Active Contributor
0 Kudos

did you checked S_ALR_87013558 report for reference.

please attached some screenshot of logic you applied.

thanks