Periodic contract : Auto change billing date of unbill in the past.

0 Kudos

Hi Experts,

I create period contract.

Example : today is 03.07.2015

contract start date = 20.06.2015 and contract end date = 19.11.2015

rule of next bill = monthly on the first of month

and tick inadvance

system will pop-up information that "there are unbilled date in the past"

I would like system automatic change billing date to 01.07.2015. Could you please recommend how can I do?

Best regards,

Jittima

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Why you want to change the standard functionality??.  Even if you try to bill the past billing date of Billing Plan tab, I believe the billing date would consider 01.07.2015 only

G. Lakshmipathi

0 Kudos

Thanks you for your reply. I just want to know that the system can be configuration to automatic check and change the billing date for a specific date in the past days to be  the current month or not. 

The system generates a bill in June. But today is July, so customers do not get the billing month in the past. Therefore, User must change billing date of the first bill to be billed to the customer on July.


Please advice me.


Best regards,