Dear experts ,

Need your inputs for the following issue,

Have a material associated with 03 inspection type ( in-process inspection)

During results recording , i am getting this 'Unit to be inspected tab'.

How to avoid this tab..?

We are using sampling procedure.

Inspection unit to be entered during results recording ..?

Could anyone guide me on this in detail.

  

  

Please let me know , how this works.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Daya  ,

As usually get this  tab when  we are working with serial numbers . If we are working with serial numbers then each serial number's result we can record seperately  & acceptenance &  rejection could be done .

As it is  Inspection type "03"  It basically follow the below process .

When we activated the Serial number profile  in matreial master then at the time of process order creation we can provide the serial number & when  process order released  then it generates the Inspection lot & this Inspection lots  contain the same serial numbers which we maintain in the process order .

We can record the Inspection result for each serial numbers.

Thanks ,

Regards,

Aman

arunsapqm
Participant
0 Kudos

Hi daya,

I hope they made some Enhancement (Tab exit) in RR screen Check with ABAPer for the following Link

Thanks

former_member184571
Participant
0 Kudos

Hi Ayoub ,

Is it possible to keep this field optional rather than mandatory.

Regards,

Daya

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

Please confirm if you are using serial numbers or handling units.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayoub ,

We are not using any serial number or handling units.

is there any possible to make this field optional.

Regards,

Daya

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

You have this because you are using the option "Recording by units to be inspected" in Recording view at the master recipe operation details (QM data for operation)

Please change that setting to default view and try again.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayoub ,

No have not used that setting. have kept it default

Please do let me know Ayoub , what other details i need to check.

Regards,

daya

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

Please share your material QM view settings as well as your inspection point definition.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayobh ,

here are the details ,

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

Please try to select "No external numbering for original values" in the field Ext. numbering at the QM data of Recipe.

Let me know if this removes the entire tab of units to be inspected.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayoub,

Have not used any option over there/ It is blank .

what may be the reason..?

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

The tab appears if you have a serialized material or you select to maintain external unit numbers at the Recipe header.

Please select the option "No external numbering for original values" so system will not ask you for that.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayoub ,

Thank you very much for your quick response .

I tried as you said , but still i am facing same problem.

What next other data to be checked Ayoub..?

Waiting for your reply.

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

After updating the Master Recipe, you need to re-create new inspection lot in order to make the system take new settings into consideration. Old inspection lot won't be reflecting these changes.

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayobh,

For each and every changes i am creating the new lot and checking.


No changes.


Regards,

Daya

Ayoub_Habchi
Contributor
0 Kudos

Hi Daya,

Do you perform re-read master data for process order too?

Regards,

Ayoub.

former_member184571
Participant
0 Kudos

Hi Ayoub,

Everytime I am creating a new process order for testing purpose which results in generating a new inspection lot.

But is there any other standard settings.?