We have plan to Migrate of SCM DB2 DB from AIX to RHEL7.

Our LiveCache LC is on SUSE Linux & will not migrate to RHEL7 as per current design unless, otherwise this combination is not supported ( Exploring more on supportability aspects).

I have below questions:(based on assumptions that LC will not be migrated)

1 - Only exporting & importing SCM DB is sufficient? If Yes, can someone outline LC related steps that I still need to perform in this      scenario.?

2 - Since I am assuming here that LC will not be migrated do I still need to runreport /SAPAPO/OM_LC_DOWNLOAD_UPLOAD            before & after SCM DB Migration to download & upload LC Objects to & from SCM DB respectively?

3 - I am checking on PAM & with SAP, meanwhile if someone already know -  Is below combination of Target is supported ?:

SAP SCM application -- SUSE Linux

SCM DB2 DB -- RHEL7.1

SCM LC - SUSE Linux

Best Regards

Sachin

Accepted Solutions (1)

Accepted Solutions (1)

former_member229109
Active Contributor
0 Kudos

Hello Sachin,

If the liveCache will be not migrated, and you will not change the liveCache server, then you dont need to run the liveCache download/upload steps.

For the project I recommend to run the steps:

- bring the SCM system to the consistent status;

- Schedule downtime. Stop the liveCache in LC10.

- Create the liveCache & SCM DB backups in sync before to start migration.

- Migrate the SCM DB.

< review SAP note -

886103 System Landscape Copy for SAP SCM

>

- Start the SCM system.

  Check the connection to liveCache in LC10-> Integration.

  Start the liveCache.

  Test connections in /ndb59, //om13 -> checks.

- Run the consistencies checks for the APO data & clarify via SAP message, if the inconsistencies occurred, before to release the system to users/CIF.

Regards, Natalia Khlopina

Former Member
0 Kudos

Hi Natalia,

Thanks for the response & the information.

I was busy with SANDBOX all these days & could reply before.

I am going to Migrate DEV system next week.

I have one question on your reply "bring the SCM system to the consistent status;"

What exactly do we need to do here?

Run program - /SAPAPO/OM_LC_DOWNLOAD_UPLOAD

& perform consistency checks in the section A of this report.

Can you please confirm on this part?

Thanks

Regards

Sachin Bhatt

former_member229109
Active Contributor
0 Kudos

Hello Sachin Bhatt,


"bring the SCM system to the consistent status;":

- Apply all recommended notes, SAP note -

1008187 - Composite SAP Note for problems with /SAPAPO/OM_LC_DOWNLOAD_UPLOAD

- program - /SAPAPO/OM_LC_DOWNLOAD_UPLOAD & perform consistency checks in the section A of this report. Click on "i" box for recommendations for each step.

- Check those & repair them.

- If any further questions/issues

=> Create the SAP message & get SAP support in time.

Best regards, Natalia Khlopina