Error Checking Work Status

Former Member
0 Kudos

While doing a load from our BW system, we had some records bomb out with the error "Line0: Error checking work status".  Can anyone provide some insight into what might be causing this problem?  We are working through kinks with the new install of our planning system and any guidance would be appreciated. 

Accepted Solutions (0)

Answers (1)

Answers (1)

Shrikant_Jadhav
Active Contributor
0 Kudos

Hi Jason,

In that work status you are nor supposed to run data manager.

Check the work status setting. Share the screen shot of the same.

Shrikant

Former Member
0 Kudos

So this is likely a dumb question, but where do you check the work status setting? 

Shrikant_Jadhav
Active Contributor
0 Kudos

Which BPC version you are using ?

If its 10.0 - Go to administrator -> Feature -> Work status .

May be helpful.

Shrikant

Former Member
0 Kudos

I grabbed a screen shot, where can i tell if something has been locked? 

manohar_pappireddy
Participant
0 Kudos


Hi Jason,

If your work status is "submitted"or "approved" it is locked for "Data manager" also.

While running DMP,you may by pass the work status

You can check work status for the intersection of the load you are trying in EPM.

EPM-->Save data-->Change work status.

Thanks,

Manohar

manohar_pappireddy
Participant
0 Kudos


Hi Jason,

Some times,some clients disable this option with hard coding.

In that case,you need to change the work status for the specific intersection to "Unlocked".

You can change the work status if you are authorized.

EPM-->Save data-->Change work status.