Multiple Shipping Calendars- CTM (Shipping to different DC on specific days)

former_member906762
Participant
0 Kudos

Hello Gurus,

We have a scenario where we are shipping only on Monday Tuesday to DC 'x' and Wednesday Thursday to DC 'y' . We tried shipping calendar but that is location specific and we can assign only one shipping calendar to the source location . I tried transportation calendar but if we have Monday Tuesday for tlane between plant and DC 'x' with a transportation duration of 4 days then the goods are reaching the DC after 2 weeks as it is taking Monday Tuesday of current + Monday Tuesday of next week = 4 days .

I want it to start on Monday and be available on Friday . Is this achievable

Regards,

Nick

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Nick,

Create a second source location as dummy location, so you will be able to assign the second shipping calendar to it.

Thanks,

Regards, Marius

former_member906762
Participant
0 Kudos

Hello Marius,

That would not work, we are currently using CTM for planning and creating an extra location/plant will cause planning to be done at 2 location when actually it is only one plant.

Regards,

Nick

Former Member
0 Kudos

Hi Nick,

You can have a dummy source location a DC center not a plant!

Thanks, Marius

former_member906762
Participant
0 Kudos

Hello Marius,

This option will cause issue with STO process and will make it cumbersome . Do we have any alternate approach for this.

Regards,

Nick