on 07-24-2015 10:21 AM
Hi,
For a material i have given my "rounding value as 5" through the path (Product portfolio"Workcenter" -> Materials "view" Planning "tab" ->Lotsize limitation rounding). But while running my MRP(Material requirement Planning) system have not rounded any value based on my demand 52PCS. Kindly provide your feedback.
Regards,
Paarthiban
Hi Paarthiban,
the way you described the system behavior it looks like a bug. Please raise an incident then. If you apply a rounding value the MRP should only create proposals according to the rounding value, in your case a proposal for 55 PCS.
Best regards,
Stefan