Issue component document made wrongly

Former Member
0 Kudos

Hi Experts,

One of my client added issue component document wrongly,Is there any easy method to roll back the issue for production documents

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

former_member205766
Active Contributor
0 Kudos

Hi Bharathi,

Open Receipt from production document and click the return component button, which is in right side bottom corner. Now you will see list of Issued document and select the wrongly added document and added the receipt from production document . Now check the inventory posting list report.

Regards,

Balaji Sampath

Answers (2)

Answers (2)

Former Member
0 Kudos

thank you experts for your solutions.

KennedyT21
Active Contributor
0 Kudos

Hi Bharathiraja.....

In receipt from Production , choose  Production  Receipt from Production

Opens the List of Production Orders displaying the production and disassembly orders.

To return components, double-click the relevant order, and in the displayed Select Items to Copy window, select the items to return.

Regards

Kennedy