on 07-29-2015 8:56 AM
Hi,
I am planning an upgrade from HANA database Revision 73 to SP Revision 100 but I'm a bit confusion. SAP recommends to stay on the current SAP HANA Support Package Stack until the next SAP HANA Datacenter Service Point is reached.
Should i proceed like this;
An upgrade from maintenance revision 73 to 82
An upgrade from maintenance revision 82 to 96
Finally upgrade from maintenance revision 96 to 100 or wait Revision of new Datacenter Service Point.
Please share your suggestions
Thanks
I believe 100 is also tested. You can go directly from 73 to 100.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tutku,
Good practice is to upgrade to SAP Production Verified Revision as that is a version that you know is stable and has been tested on a production instance. Currently it is at Revision 96 if I'm not mistaken so my suggestion is to upgrade to that revision especially if you are on a productive system.
As for how to proceed, I believe you can upgrade directly from revision 73 to revision 96 as every revision is backwards compatible. No need to go through revision 82 first. Hope that helps.
Regards,
Robert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.