on 07-30-2015 2:24 PM
Hi All,
Budget Assigned value in CJ31 is showing rs.90,000 for one WBS, for the same WBS in S_ALR_87013558 actual values is showing correctly but commitment value is showing wrongly total assigned value is rs.1,00,000. why it showing difference.
I have ran program RKANBU04, CJEN and CJBN but still it's showing same value.
Please suggest on this.
Hi,
Do you mean in CJ31, the assigned value is 90,000 and
in S_ALR_87013558, the actual value is 90,000 while the commitment is 10,000, which makes the assigned value 100,000?
As mentioned in note 1414563, the update logic is different between PS reporting and CJ31.
Do you have any exempt cost element? Or value with value type 60 involved?
These all can be reasons for such a difference.
Best regards,
Miya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Miya,
Thanks for Reply,
In S_ALR_87013558, the actual value is 90,000 while the commitment is 10,000, which makes the assigned value 100,000. i have checked there is no exempt cost elements.
Except CJ31 i am getting 1,00,000 assigned value in all reports (i.e.S_ALR_8073542,S_ALR_8073558,CJI5, CJI3).
Best Regards,
Siddu.
Hi Siddu,
Please run CJ31, menu: extras->availability control-> analysis.
Through the analysis report, you can see how the assigned value is built and you can compare with PS reporting, and see where the difference is.
Note 1414563 also describe some other possible reasons for such difference.
You can also check this note and see if it gives some hint.
Best regards,
Miya