Query Material Actual Cost for Period of time

Former Member
0 Kudos

Hi Experts,

The user requests me to query the actual cost for some particular material code. I know that by using T-Code MM03 I can view the material code actual cost for the current period and the previous period. However, the user wishes to view the actual cost for longer period of time. For instance, if users want to view the actual cost of the material code for two years period, is there any T-Code or table that is able to perform this?

Thanks.

Regards,

Wayne

Accepted Solutions (1)

Accepted Solutions (1)

ArturoSenosain
Advisor
Advisor
0 Kudos

Hi.

Check this old post written by Mr Jurgen.