Service Master Long Text editable in PO

Former Member
0 Kudos

Dear Gurus,

Need help for converting service master long text from display mode to editable in service PO. In screen shot it is shown as service text besides line item text.

I tried below options but still not able to get desired result -

1. Spro-Purchasing - PO- define screen layout at document level -

ME21N

ME22N

2. Material Management - E Service Management - Define Screen Layout

Please suggest at the earliest.

Regards,

Manoj

keyurpatel2607
Explorer
0 Kudos

Were you able to resolve this issue?

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member183424
Active Contributor
0 Kudos

Everything is there in your second option. Img path OLMSRV-Define Screen Layout

Check the field selection key 4, ME21, ME22, NB, PT9.

You can find the Service Short Text in service field under the field selection key.

Former Member
0 Kudos

Hi Dibyendu,

need service long text from master editable in PO.

Regards,

Manoj

former_member183424
Active Contributor
0 Kudos

I am also talking about the same. System will check the service screen layout for the service tab in PO line item.

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

When you are creating service order with entering service master/activity number and want change description of service master in service order itself, then maintaining description of service master in service master in t.code AC03 is meaningless.

Or if business required- you can create service order without service master/activity number by entering your favorable text description

Regards,

Biju K

Former Member
0 Kudos

Hello sir,

You are right, but the requirement is it should be changeable.

request to guide me on that.

Regards,

Manoj