on 08-03-2015 9:41 AM
Hi,
I have the following matter with the production settlement.
The issue is the following; we create a sales order with variant configuration to configure a product. This, in turn, has a configuration component in its BoM. Therefore, once the configurations are done, an the sales order saved, the system creates two planned orders that will become on two production orders. A main PO engagged to the sales order and a second PO created due the main PO.
The matter is that when I try to settle the POs against the sales order I have no problem with the main PO. I mean, with the PO created directly by the sales order. But when I try to settle the PO created due the main PO the system doesn't allow it because this PO is not engagged directly to the sales order.
¿How can I settle the secondary POs?
thanks a lot.
OCS.
Hi,
We create the production order against the sales order that PO can settled to sales order when sales order is a cost object.
In your scenario second PO is not engaged directly to the sales order mean that PO is not specific customer requirement ( sales order is a not cost object scenario) that one can settled to either material or PSG (profitability segment) as per the settlement rule.
Regards,
Naresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.