We are using LPA scheduling agreements with kanban (manually event). The article ordered has a base unit of LB. The kanban quantity is based on a nominal weight. The vendor ships and bills at actual weight.
Each kanban requests triggers a SA release.
For example, we have two requests, each for 150 pounds of compound for a total of 300 pounds
Vendor ships 155 pound. The inbound delivery will fill the kanban and post 155 into stock. Per MRP, that now leaves us with a balance of 145 pounds.
Vendor ships 140 pound. The inbould delivery fills the second kanban and post 140 pounds into stock. Per MRP, now have 5 pounds open.
Question - how to close the 5 pounds?
Thanks,
Marcus Lowe
Hi,
Are you not expecting any more GRs/IBDs for this line item. ? Double click on line item in scheduling agreement and try to tick delivery completed indicator in GR/IR control tab. This should close the 5 qty in MD04.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.