on 08-04-2015 7:05 PM
Hi PP experts,
There are some issues about production order cost, I cannot see the Labor Costs and Machine Costs in CO03-->Goto-->Cost-->Analysis as below:
Then I go to t-code CO15, the screenshot of order confirmation as below:
Is there anything wrong in order confirmation? Could you please guide me how can I display the Labor Costs and Machine Costs? Thanks.
Regards,
Steve
Hi,
Check the order cost report KKBC_ORD
Also Check that Production Order has any cost calculation log in CO02 --> GOTO ---> LOGS ---> COST CALCULATION
Regards,
Naresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Steve,
I guess the activity type (machine, labor ) costs are not picked up in Cost Estimate.
Try to execute CK13N for the material and see whether the activity are picked up in costing.
If the activity cost are not picked up, check and verify the assignments of activity type in the work center.
regards,
karthik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please check if activity types are maintained correctly in work center costing view for machine and labor against the cost center using CR03.
Then check if planned hours are for machine labor are maintained in the routing.
Post that check if activity rates are maintained in KP26 for cost center and activity types.
You should atleast see the planned costs if values are maintained in routing, actuals if not entered will be zero and system should show variance.
Please check the above points and get back, if you still are not able to figure out
Best Regards,
Ameya B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ameya,
Thanks for your reply first.
I have check points which you advised.
Please check if activity types are maintained correctly in work center costing view for machine and labor against the cost center using CR03.
---> Yes, the activity types are maintained in work center.
Then check if planned hours are for machine labor are maintained in the routing.
---> Yes, the hours are maintained in routing.
Post that check if activity rates are maintained in KP26 for cost center and activity types.
---> I cannot find the field 'activity rates', but I can find the field 'Fixed price' in KP27 and it has value.
You should atleast see the planned costs if values are maintained in routing, actuals if not entered will be zero and system should show variance.
---> Sorry, I cannot understant your meanings, could you please explain it detailed or give some screenshots?
Regards,
Steve