Report on partial budget release (Funds Management)

Former Member
0 Kudos

Hi,

I posted budget in Fund Center 'A' against commitment Item 'XYZ' using transaction code "FMBB" of $100,000. I only released $40,000 from it, now i am unable to find any standard report that will show me total budget entered, released and remaining amount available for released.

Please share report (IF THERE IS ANY) which can provide such details.

Regards.

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

You can use FMKFR01 and run it on SAP-provided key figures for released and introduced budget, e.g. CURRENT_RELEASE, etc. Alternatively, create your own key figures (but, standard ones should be sufficient) or build a report, as suggested by Aleksey.


Regards,

Eli

View solution in original post

2 REPLIES 2

Former Member
0 Kudos

hi, there is no such standard report.

you can create your own via GRR2, group 4FM

iklovski
Active Contributor
0 Kudos

Hi,

You can use FMKFR01 and run it on SAP-provided key figures for released and introduced budget, e.g. CURRENT_RELEASE, etc. Alternatively, create your own key figures (but, standard ones should be sufficient) or build a report, as suggested by Aleksey.


Regards,

Eli