Hello experts,

My 558 report shows the different assigned values than cj31.

for assigned we have only actuals and when we check in CJI3 we see the similar to CJ31, I tried all correction programs too.

when i did another analysis found 558 is not considering 2014 values and taking only 2015 values whereas AVAC is active on overall.

please the below screenshots and throw some light to brighten the darkness.

Thanks,

Vindhesh

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member412338
Participant
0 Kudos

Thank you guys,

I checked but still not able to figure out the root cause.

Please help me out to undertstand this problem.

Thanks,

Vindhesh

sunil_yadav2
Active Contributor
0 Kudos

Hi Vindhesh,

please check below screenshot and check as per suggested by Maria.

thanks

Sunil

MTerence
Active Contributor
0 Kudos

Hi Vindhesh,

Check in CJE6, whether any changes done to Assigned values, which has resulted to limit 2014 values.

In standard, Assigned value is 558* is an addition of Actual / Budget / Commitment

Regards

Terence