on 08-21-2015 11:05 AM
hello,
In calculation of remaining order plan value, plan values of the material which are maintained as project stock (indicator 2) are not considered in remaining order plan but when these materials are issued to production order, that actual cost are being considered in calculation of remaining order plan. This results in lower value of remaining order plan calculation which is wrong.
Can you please suggest the way so that actual cost of such materials should also not be considered in calculation of remaining order plan value.
Regards
Kalpesh Agrawal
You can switch to non-valuated project stock so the actual costs are posted to the WBS at Goods Receipt rather than later at Goods Issue.
Looks like you are running valuated project stock where the material value is held in inventory and not expensed to the WBS at GR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.