on 08-25-2015 8:57 AM
Hi,
We observed a strange behaviour that when the application connection id is routed through the backend connection hosted on to the integration gateway on SMP, the Edm.DateTime field show a day prior to the one in the SAP System whereas if we change the backend connection directly to the Netweaver Gateway System, it shows fine. For e.g if a date is of 24th August, the application running with the backend conenction of Netweaver Gateway shows the proper date of 24th August but the one having the integration service background shows the date on 23rd August.
Is this a limitation of SMP Integration Gateway.
We are running on SMP 3.0 SP7.
Appreciate your response if anyone has faced or is are aware of this issue.
Thanks,
Rakshit Doshi
We solved this issue. It was the time zone issue. Integration Gateway uses the system time and not the timezone. Changed the time zone to UTC Coordinated Universal Time on the SMP Server and it worked fine.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rakshit,
this sounds like a product issue. Could you please raise an incident so that we can investigate this?
Thanks and regards
Björn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
13 | |
13 | |
11 | |
11 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.