Collective order scheduling

former_member240058
Participant
0 Kudos

Hi

I am using collective order and with order finish date like 01.10.2015.

System does todays scheduling as start date goes in past, with this system does todays scheduling for sub orders and header orders.

Now both orders are starting at same date.

How to have header order after suborder  finish date, if start date of suborder goes in past.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Mayuresh

You should provide more details when opening a thread. Is this a planned or production order? How are you running scheduling for these orders?

BR

Caetano

former_member240058
Participant
0 Kudos

Hi Caetano

We are using process order creation using COR1 Transaction with backward schedulling.


In OPUZ, start in past has 0 days.

former_member240058
Participant
0 Kudos

Hi All

Please can you reply

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You are using a process order, therefore, you must define a FS relationship on the master recipe.

BR
Caetano

former_member240058
Participant
0 Kudos

Hi Caetano

If start date of suborder is not in past in then superior order will start only after suborder finish date.

former_member240058
Participant
0 Kudos

Hi

Please can anyone reply, How to start superior order after suborder if start date is in past.