on 08-31-2015 1:57 PM
Hi experts,
I wonder if it is possible to modify the way to obtain the actual start/end dates when the work order is confirmed.
I want thtat the system doesn't take into account the external operatioins to calculate these dates.
Is it possible?
Thanks in advance.
You can bulid your logic for dates and default the same into the confirmation screen while carrying out confirmations through IW41 or IW44, by using user-exit CONFPM01.