Hi All,
I made Alternate Routing for all the items in my plant. ie., each Component/Assembly have two routings.
I have scenario where Planned orders will be converted to production orders using collective conversion
I use MD50 for creating Planned orders, for converting Planned orders to Production orders I use CO41, at this stage I need to select desired Routing.
The above requirement is detailed below.
1. The settings has to be done in such a way that, before collective conversation of planned orders, I need a pop-up option for selecting desired Routing, ie., either original routing or alternate routing to effect the orders.
Please suggest how to make this settings and where to make.
Regards
Benarjee
Hi Banerjee,
Check the "order type dependent parameters" of production order type you are using. (t code OPL8). Chnage routing selection to manual. Make sure that you are alternate sequence marked in your case.
Regards,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.