Hi
Can someone assist in helping me on scheduling reports.
In Cabi 4.1 sp3 the reports is running for 2 days and suddenly the reports failed on the third day. then we need to reboot our server then the reports work perfectly for 2 days.
the error we receive in event viewer:
The scheduler component failed the object identified by 242710. The job associated with the object was unresponsive.
on the report error message:
Object failed to run due to an error while processing on the Job Server.
we did add xmx8g to the adaptive job server but we are still experiencing the same error.
on Boxi 3.1 we did not had this issues reports is still running smoothly.
Hi Gavin,
Please test the following:
Save the report to a different folder with a different name. Then save it back
to the original location with the original name then test schedule again.
For more details, please check the following KBA:
1852375 - Error: "Object failed to run due to an error while
processing on the job Server" when scheduling a WebI report
http://service.sap.com/sap/support/notes/1852375
Kind regards,
Wafa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.