Problem with EPMLink after SP19 (build 8936)

0 Kudos

Is anyone found a solution for this issue?:

I use EPMLink to connect an input schedule to another input schedule and this process worked fine through SP19 (build 8936). Sometime after that SP (currently on build 9188) when double clicking on the EPMLink, the other input is called but doesn't fully load correctly. But if you click on the new input's sheet tab the input loads correctly and functions normally

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Bill

This may be caused by Microsoft security updates.

SAP notes 2219713 and 2107965 describe issues with a variety of symptoms that are caused by Microsoft updates.

The only changes around the EPMLINK or EPMPATHLINK functions that have been release after SP 19 are described in the following SAP notes:

2124009 (SP21)

2095546 (SP20)

Stefan

0 Kudos

Thanks Stephan,
These notes don't specifically address the issue I am experiencing but they do highlight the Microsoft update issue. Unfortunately Support can't test all possible functionality and I at least have a workaround for this issue. Hopefully a fix will be coming through the system shortly.

Bill