on 09-28-2015 10:37 AM
Under activity maintenance rules Check_time_base is set TRUE.
In routing activity is enabled pre complete.
Some components are not assembled in reqiured operation, but system let's complete anyway.
What and where I can check more to activate timebased component checking?
BR,
Kalmer Kand
Hi Kalmer,
Please check that your setup is in sync with the recommendations provided by the online help:
http://help.sap.com/saphelp_me150/helpdata/EN/96/5f0276b50545c9b83f7130a5b928f5/content.htm
In particular, MISSING rule needs to be turned on.
Also make sure you are on the latest patch. And if the issue still persists, then please submit a support ticket.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We have system 6.0.4.35.54.
And here is CT config.
When enable activity CT520 in routing I get error that reports 6 missing components (Message 13920).
In SFC BOM there is that assy operation behind two components (no ref des) both with qty 1.
And in bom total there is 117 components and do not see any pattern where that number 6 is coming.