10-01-2015 8:23 PM
I’m using transaction MILL_OC to convert a bunch of planned orders into a single Mill Products Production Order.
The Scheduling Margin Key is missing from the Production Order. If I create a Production Order using CO02 the Scheduling Margin Key copies to the Production Order.
Any idea why the Scheduling Margin Key does not copy into the combined Production Order when using MILL_OC? Thank you very much!
04-25-2016 6:24 PM
Hello Ann
I know that this is an old thread, but as it is unanswered and I found an explanation, I'm sharing it with you.
According to note 597237, the scheduling margin key of a combined order is always 000. That's because you can combine different materials, with different scheduling margin keys and system would not know which key should be used.