Hi Team,

When sufficient budget is not available during activity confirmation, system update confirmation without actual cost. I want system should not update confirmation if no sufficient budget available how to configure this

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Lalita,

First thing, go to OPST, whether the Actual Costs and Termination for Incorrect Act.Costs are ticked for Logs / Error Handling

Regards

Terence

Former Member
0 Kudos

Hi Maria,

Yes it is active still system confirm activity with hours but actual cost not posted as no sufficient budget.

Also during activity confirmation sufficient budget available at WBS level but still system check plan cost of activity why?

MTerence
Active Contributor
0 Kudos

Hi Lalita,

Sorry, i misunderstood something here.

What is your exact requirement ?

Do you want to stop confirm activity, if there is no Budget ?

How is your system is behaving ?

Regards

Terence

Former Member
0 Kudos

HI,

1. if no sufficient budget, system should not update confirmation.

MTerence
Active Contributor
0 Kudos

Hi Lalita,

Refer below thread

Confirmation Not Required without calculation o... | SCN

Also, check whether the tolerance group ++ is maintain in SPRO

Project System - Costs - Budget - Define Tolerance Limits

Regards

Terence

Former Member
0 Kudos

hi,

activity plan cost is 1000$ for 10Hrs. When I try to confirm it for 13 Hrs budget error get. But there is sufficient budget at WBS level....can system check WBS budget rather than activity plan cost

MTerence
Active Contributor
0 Kudos

Hi Lalita,

It will be checking at WBS element level only.

Kindly share the screenshot of S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned

Regards

Terence

Former Member
0 Kudos

I try to confirm activity 0100, but system check and confirm only for Rs.4000. But suffcient budget is available WBS as 25850

MTerence
Active Contributor
0 Kudos

Hi Lalita,

If you try to post confirmation again, is the system allows ?

You need to check whether any Validation in place, which does the check.

Regards

Terence

Former Member
0 Kudos

if i try to post confirmation system allow with message..no actual cost calculate. It will update only hours with no additional cost...

MTerence
Active Contributor
0 Kudos

Hi Lalita,

What is the message it displays ?

Kindly attach the screenshot the error message.

Regards

Terence