When sufficient budget is not available during activity confirmation, system update confirmation without actual cost. I want system should not update confirmation if no sufficient budget available how to configure this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lalita,
Refer below thread
Confirmation Not Required without calculation o... | SCN
Also, check whether the tolerance group ++ is maintain in SPRO
Project System - Costs - Budget - Define Tolerance Limits
Regards
Terence