Dear expert ;

Is there any way to know when the work center is locked ?

thank you

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

You can see if a work center is locked clicking on the button "administrative data" of the first tab.
See the screenshot below:

BR
Caetano

tiwary_vinita10
Participant
0 Kudos

Hi Caetano,

I want to unlock multiple locked work centres as it is causing issue in closing projects in CJ20n. Can you suggest, how can I do that?

Thanks!

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Vinita

This is a question that was originally posted in 2015, and we typically avoid resurrecting this kind of old thread.

Would you please open a new thread with your question?

Regards,
Caetano

Answers (4)

Answers (4)

amal_kamal
Active Participant
0 Kudos

Thanks for all of you ;

the issue is that i want to create a z report that exclude the locked work centers starting from the date of the lock

solomon_macwan
Active Contributor
0 Kudos

hi Amal,

if you need a report where it displays all the active work centre then you don't need to create report.

In CR60 create a layout where you filter the blocked work centre.

regards,

Solomon

amal_kamal
Active Participant
0 Kudos

I need to know the date when the work center is locked

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

As far as I know, this information is not available on the system. You can only find the date of the last modification, but you cannot guarantee that this is the date where the status was set.

Also, please provide a more detailed description of the issue when opening a thread. Your initial question was "Is there any way to know when the work center is locked?" and for me you are simply asking is the work center is locked or not. See the blog for more details.

BR
Caetano

pravin_kusumbe2
Participant
0 Kudos

Hi

The Date will be same as the change date in CRHD. You can not Put a different from date for locking the work center.

Pravin

solomon_macwan
Active Contributor
0 Kudos

hi,

use transaction  - CR60

then change the layout for LOCKED - go to main menu > setting > layout >current

please reward if helpful

Solomon

amal_kamal
Active Participant
0 Kudos

thanks for your reply , I know how to know if the WC is locked or no , my question is that i want to know it is  locked from which date?

ameya_beri
Active Contributor
0 Kudos

Hello,

You do not have the ECM function available to change work centres, so you do not have the valid from date when you lock.

Once it is locked it becomes immediately locked from current date, and you get a warning when you try to use it.

Locking and Unlocking Work Centers - PP - Work Centers - SAP Library

Hope this helps

Best Regards,

Ameya B.

marianoc
Active Contributor
0 Kudos

Hello,

Check in SE16, table: CRHD.

The work center is the field: ARBPL and the lock status is the field: XSPRR.