Dear PS Experts,
If stock is available at grouping WBS and now needs to be issued to child level WBS then :
1- Can direct good issue be done from grouped WBS to child level WBS.
OR
1- First Transfer posting is made from grouped WBS to child level.
2- Then good issue is done.
Please Provide assistance .
Thanks indeed,
Hi Ankit,
I believe that for valuated project stock scenario you will need a second option that is transfer + issue.
Check with MM colleagues on what movement types are available.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As I think, first transfer posting & then GI seems to be correct. But as Maria suggest, check with your MM consultant for exact processing as per your business process.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.