on 10-06-2015 10:44 AM
Hi,
I have created an internal activity and assigned work centre on which activity type with it's rate is already assigned.After releasing activity that activity I got plan price but when I'm going to confirm that activity, I got below error.
So kindly tell me how to get actual cost after activity confirmation.
Regards,
Faizan
Hi All,
I got solution why actual cost was not showing, actually in after defining planning cost rate in KP26 for actual cost KBK6 rate for actual needs to define which was missing so after defining it I'm getting actual cost after confirmation.
Regards,
Faizan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try to check budget availability. May be your activity requires more budget that available. If it is, then supplement required budget & try to confirm again.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Faizan,
Execute COFC and check the error
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Maria,
As you suggested I execute COFC so after running it I got below error.
I have already check in KP26 that rate for cost centre 1030811001 with activity type PS_WC already defined but still getting this message while confirmation of internal activity.
Any other suggestion?
Regards,
Faizan