Updating Project WBS element from Campaign data

former_member188321
Contributor
0 Kudos

Hi Experts,

when a campaign is saved in CRM, a BDoc 'MKTPL_MKTELEM' is triggered by Standard code which reaches ECC and update few standard fields in PS - Project/ WBS element. Now there is a field in CRM Campaign, which exists in the mentioned BDoc message as well. This field value should populate in a Z-field at WBS element.
Question is, where to map these fields? How does ECC knows which field of BDoc message should be populated to a field in WBS element? Is there any FM/Exit/ BADI for this?
Since this is generic question on a standard feature of PS update, you may not need to look into DCM specifically.
Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188321
Contributor
0 Kudos

Hi Experts,

Can anyone answer this?

Regards,

former_member188321
Contributor
0 Kudos

found it myself, hence closing the thread.

beam_s
Explorer
0 Kudos

Hi Damandeep,

I am facing the same problem, I dont know how to assign my crm zfields in the WBS element.

I can see the fields exists in the BDOC traveling to ECC, but cant find a place where to ssing to the right fields in ECC WBS.

Regards