on 10-09-2015 1:24 PM
HOW TO RAISE THE REQUIREMENT OF BOM- CHILD MATERIAL WHILE USING FOLLOWUP MATERIAL IN MATERIAL MASTER AUTOMATICALLY?
B IS THE CHILD PART OF A
C IS FOR FOLLOWUP MATERIAL OF B WHICH IS DONE IN MM02
WHEN RAISING THE REQUIREMENT, THE REQUIREMENT IS RAISED FOR C. BUT WE WANT B TO BE RAISED THROUGH MRP RUNNING
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
B IS THE CHILD PART OF A
C IS FOR FOLLOWUP MATERIAL OF B WHICH IS DONE IN MM02
WHEN RAISING THE REQUIREMENT, THE REQUIREMENT IS RAISED FOR C. BUT WE WANT B TO BE RAISED THROUGH MRP RUNNING.
I already done what Mr.Rohit says.
As Mr.Rohit says, why do i need to set this dicontinue indicator if i dont need the existing material. if it is required i will delete from the BOM itslef. why i have to make it complicated.
Hi Mahendran,
As per my understanding C is the follow up material for B.
For this you have to make setting material master of material B with date and follow up material.
Then after MRP run the requirement after discontinue date fulfill bye follow up material C.
System check only date not stock.
Thanks and regards,
Pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.