Report with periodic view of Planned Hrs

Former Member
0 Kudos

Hi,

Quick question, can anyone suggest a PS report which gives you periodic view  of planned hours. possibly in fiscal period.

we are not using workforce planning, we just plan hours on internal activities.

But want to see the planned hours by fiscal period.

Thanks,

Krishna

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member388328
Active Contributor
0 Kudos

Hi Kirshna,

What is that you are looking for .. I did not get your requirement.

Thanking you

Vengaiah

Former Member
0 Kudos

Hi Vengaiah,

Thanks for responding.
Let me explain..

I have WBS with internal activities and I have planned work on them and scheduled them.

say 500 Hrs spread across 3 months

I am looking for a report which shows

]

Month    Planned Hrs    Planned Cost

M1            200                    10000

M2             200                    10000

M3              100                    5000

There are many reports for planned cost break up but I couldn't find any with planned hours.

And its ok if I don't have planned cost in the same report. I just need the planned Hours in a monthly breakup for a WBS

Thanks,

Krishna

former_member388328
Active Contributor
0 Kudos

Hi Krishna,

use this report S_ALR_87100186...

Let me if this works for you are not...

Thanking you

Vengaiah

Former Member
0 Kudos

Hi Vengaiah,

No. This again gives me only the cost month wise.

I am looking for Planned Hours

Thanks,

Krishna