Dear SAP Experts,
Some times our production planner team forget to insert an operation called "QA inspection" within the routing.
When we notice, it is already late; and sometimes the production order has been created (CO01 transaction) , or is in subsequent stage.
It is there a SAP standard procedure, functionality or enhancement to avoid this?
Thanks in advance for your help
Best Regards
Fernando,
Try with below user exit PPCO0019 Checks for changes to order operations
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Fernando,
May have a look at and try user-exit CPAU0001 for your issue.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
If it is possible create reference operation set to create the Routing,where we can include " QA inspection" as a operation.Other operations user can modify or create at the time of routing creation.
Regards,
Velmurugan S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.