Dear Fiends,
I am scheduling PPM for quarterly maintenance and my schedule should be only on workdays i.e. Sun.Mon,Tue,Wed and Thr.
For this I have selected Factory calendar but my schedule is not working as per my requirement. I have attached IP01 and IP10 screen shots.
I am expecting below schedule from my maintenance plan.
MM/DD/YYYY
11/15/2015 Sun
2/15/2016 Mon
5/15/2016 Sun
8/15/2016 Mon
11/15/2016 Tue
2/15/2017 Wed
5/15/2017 Mon
8/15/2017 Tue
11/15/2017 wed
2/15/2018 Thu
5/15/2018 Tue
8/15/2018 Wed
I have fixed the above issue by correcting scheduling period, Holiday calendar and Factory calendar.