Former Member
0 Kudos

Dear Experts

I want to write object dependency for PDS in APO to select particular resource when planned order generated . i have seen the option under T-code PDS_maint . how to mantain .please suggest

scenario for example :

I have 10 resources . i want to make one of X resource to be selected always when ever planned orders are generated .Pls suggest

I can do these through procurement priority . But I want do these through object dependency

Regards

Jaisree

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Experts

Any help on the above query

regards

Jaisree

Flavio
Active Contributor
0 Kudos

Dear Jaisree,

maybe the OSS note 946890 could be of some help.

Particularly, please have a look at the zip file attached to the note solution, it contains an explanation for a variant function Z_SET_RESOURCE that could hopefully help.

Thanks and bye,

Flavio