SAP CPM (Commercial Project Management integration With PPM(Project Management)

0 Kudos

Hi All,

I am doing some solution design for one of our client, I have a question related to Commercial Project Management(cpm) Integration with PPM Project management which is as under.

I am very well aware of CPM integration with PPM when it comes PS Project creation from PPM item.

Just wanted to know is it is possible we can link CPM master project with PPM project Management (cProejcts)...since we want to use project management features given in Project management/Resource management i.e (phase, task......roles.. resource and assignment of resource to task ..etc) of PPM and later linking master project with SD for billing related features available in CPM....

Thanks

Amit Mishra

1 ACCEPTED SOLUTION

a_vanengen
Explorer
0 Kudos

HI Amit,

yes it is possible to link the cpm master project to the ppm project in project management. in that case you can see the structure of the project with the phases and the tasks in your cpm structure view.

via a relationship between ppm and ps project you will see all actuals posted to the assigned wbs elements in cpm reports via the ppm objects.

IN Financial planning you can plan your costs and revenues on the ppm objects, however be aware that the ppm objects are not replicated to embedded bw by default. Here you have to create some bw configuration yourself.

regards

Albert van Engen

View solution in original post

8 REPLIES 8

a_vanengen
Explorer
0 Kudos

HI Amit,

yes it is possible to link the cpm master project to the ppm project in project management. in that case you can see the structure of the project with the phases and the tasks in your cpm structure view.

via a relationship between ppm and ps project you will see all actuals posted to the assigned wbs elements in cpm reports via the ppm objects.

IN Financial planning you can plan your costs and revenues on the ppm objects, however be aware that the ppm objects are not replicated to embedded bw by default. Here you have to create some bw configuration yourself.

regards

Albert van Engen

0 Kudos

Thanks Albert,

Does it has specific setting ? I am able to do setting for PS project but unfortunately not for PPM project management.

Br

Amit Mishra

0 Kudos

Hi Amit,

in the CPM masterproject customising (SPRO) you can assign the cProjects objects to the masterproject type. (Object types DPO, PPO and TTO) please be aware that you have to assign the logical system (Where PPM is running on) has to be assigned to the DPO object type.

If you use Financial planning as well, information for the structure elements of cProject (Definition, Phase and Task) has to be replicated to the embedded BW environment.

Where for the PS objects this replication takes place via a Deamon, and by SAP delivered BW objects, for cProjects you need to do a littlebit more your self.

See note 1806291, step 10 where it is explained how to replicate these objects using standard BW content.

regards

Albert van Engen

kenmelching
Active Contributor
0 Kudos

The CPM Master Project can link to PPM, MRS, PS, SD, and CRM objects simultaneously.  This is standard CPM delivered object links.  You can also create additional links per your requirements with the delivered framework.

0 Kudos

Thanks Ken,

How to do it for PPM and MRS?

Unfortunately I am unable to get right setting...

Thanks

Amit Mishra

0 Kudos

Refer to the CPM installation Admin Guide on how to link external systems.

MRS link says to see Note 1806291.

You will need basis help.

0 Kudos

Thanks Ken,

Br

Amit Mishra

mariano_sabiche
Active Participant
0 Kudos

Hello Amit;

For an example full process between SAP CPM, PPM and PS for CAPEX, you will have this steps:

01) Create Proposal Item (SAP PPM with Fiori)

02) Review Portfolio Structure (SAP PPM, optional)

03) Questionnaire's and high level Financial Planning (SAP PPM)

04) Decision Points and Approval (SAP PPM with Fiori)

05) Detailed Financial Planning (SAP PPM)

06) Review and Scoreboard (SAP PPM)

07) Create PS project from Portfolio item (SAP PPM)

08) Transfer Budget from Portfolio Item to PS Project (SAP PPM)

09) Master Project creation and linking of PS project (SAP CPM)

10) Maintain Project Team Members (SAP CPM)

11) Perform Financial Planning (SAP CPM)

12) Transfer Planned Cost from CPM to PS Project (SAP CPM)

13) Budget Distribution and Reporting (SAP CPM)

14) Create Purchase Requisition from the Project (SAP ERP)

15) Create Purchase Order (SAP ERP with Fiori)

16) Goods Receip (SAP ERP with Fiori)

17) Time sheet (SAP ERP with Fiori)

18) Creation of Issue (SAP CPM)

19) Creation of Change Request (SAP CPM)

20) Creation of Cost Estimation Alternative (SAP CPM)

21) Cost Estimation Approval (SAP CPM)

22) Checking the Approved Cost (SAP CPM)

23) Transfer of revised planned cost to PS (SAP CPM)

24) CPM Other Functionalities like Status Reports etc, (SAP CPM)

25) Forecasting (SAP CPM)

26) Risk Management (SAP CPM)

27) Progress Analysis (SAP ERP)

28) CPM Analitycs and Reporting (SAP CPM)

29) PPM Reporting (SAP PPM)

Regards,

Mariano