on 11-23-2015 3:25 PM
Dear Sir,
I am having a concern regarding TECO date and time.
PM Order created by Iw31, Release order and Issue Consumable material( Coollant) and later Later Confirm Labor activity Iw41 and do Technical Completion.
Client want to know on which date we did Technical Completion and How Much total Time is spent in closing the Order(TECO). Client want to see TECO date and time at which it happened
Sometime One single PM Order complete take two days ( Work withheld because of some reason).
Completion date I can see in Planning tab of the Order but this date is same as confirmation date.
Thanks
Hello Vikas,
The answer to your query is JCDS table.
If you want this in reports, you need to get it developed by an ABAPer, where you will also be able to calculate the Duration upto TECO.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.