on 11-24-2015 2:14 PM
Hi.
I have generated a process order. Transfer requirement (TR) was generated automatically. Based on the TR, Transfer Order (TO) was created and confirmed.
Goods issued was not done to the process order. Now i want to change the status of the process order from REL to CRTD to change the batch no of one material. It is possible to cancel / reverse the TO at this stage.
Once the TO is confirmed you cannot the cancel the same. You need to create a new transfer order.
There is an option with LT0G but its only for TO for deliveries.
Regards
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks KK,
we are stuck up at one stage.
We received one raw material and did the GRN. Then we moved this to two handling unit and the inspection lot was generated.
Before QC clearing the inspeciton lot we transferred the raw material from one code to another code using vlmove. In this process earlier inspection lot also got moved, but the material is gone to unrestricted status ( in the new code).
Then we created the process order using the second materia and , TR generated automatically and TO got confirmed. But when we try to issue the material based on this process order system is showing an error of "HU ITEM REFERES TO AN INSPECTION LOT - MSG 320 - HUGENERAL".
Now we are trying to release the HU from process order, system is not allowing us. How we can resolve this.
Please suggest suitable solution .
Regards
Rajendra