on 11-25-2015 1:51 AM
I create a Long term planning Scenario (MS31), I can find the 'DepReq' requirement in MD04, but I can't find it in MS04.
The system display only 'OrdRes' ?
What's the problem?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You can have the Simulative dependent requirement. Simulative dependent requirements (DepReqs) exist in the Stock/Requirements list of long-term planning (MS04) MS01 is generating simulative dependent requirements to cover these independent requirements,
but if you run LTP for raw materials it even create stimulative planned orders.
Check if you have number range define for Simulative dependent requirement in MD93 or OMI2
Please refer useful SAP help link,
Creating and Releasing a Planning Scenario - Long-Term Planning (PP-MP-LTP) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank for your reply!
I give an example to my question :
There is a material 00B0007, many Parts use the material, so when I use MD04 ,I find two type of demand, one is requirement of production order, another is requirement of plan order;
Date MRP element MRP element data Rec./Reqd.qty Available qty Stock
2015-11-20 OrdRes 12Z00050005B001 3- 3-
2015-11-22 OrdRes 12Z00050005B001 2- 5-
2015-11-28 DepReq 00D1750 6- 11-
Now I use MS04, system can't display the third item , only two items.
Date MRP element MRP element data Rec./Reqd.qty Available qty Stock
2015-11-20 OrdRes 12Z00050005B001 3- 3-
2015-11-22 OrdRes 12Z00050005B001 2- 5-
So when I MS02, the simulate plan order don't calculate the demand : DepReq 6-.
How can I do ?
I have set depend.reqmts for the planning scenario, run MRP via MS02;
The relevant requirement were generated: SimReq ; and system generated the simulative plan order.
That looks normal.
My problem is that the operative relevant requirement don't be displayed in MS04.
( DepReq 00D1750 6- )
Then the simulative plan order qty will lost the parts of DepReq.
Hello,
I check many materials , only display the 'OrdReq' type of requirement(MS04).
In MS12 there is components, and these materials look normal in MS21.
I think the problem is about the operative requirement, they can't be calculated in simulative planning, because I have created the independant requirement for a material (MD61), the BOM of the material can exploded normally, and the component can be calculated in simulative MRP(MS02), and system generate simulative plan order for the component.
I set individual / collective indicator = 2, MRP type = 'PD'.
I feel very confused.
Best regards.
Hello,
Please refer SAP help document,
Executing MRP for Long-term Planning - Long-Term Planning (PP-MP-LTP) - SAP Library
At finished product level, the system creates simulative planned orders for the long-term planning version of the demand program.
Simulative dependent requirements and simulative planned orders are created for the components.
The check box in the planning scenario that is related to consumption based planning, will only allow creation of dependent requirements for consumption based planning meaning that only if they are part of a BOM it works.
SIM-RQ = Sim. dependent reqmts as per OMD5
After MRP run generated planned order for SIM-RQ
Simulative dependent requirements and simulative planned orders are created for the components.
Best Regards,
R.Brahmankar
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.