dear experiment ,
in the preventive maintenance , if any report to check maintenance plan if the user forget made deadline monitoring ??
thanks
Asjad
Hi,
There is no particular report for this. You could use transaction IP19 as a scheduling overview tool.
-Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You will see a 'planned date' and 'call status' fields. Where the planned date is in the past and the status is not called then this may indicate a need to check the plan further. That may show it is not being actively scheduled. This is not ideal but is the closest standard report to what you are looking for.
-Paul