on 02-05-2016 10:21 AM
Hello ,
No need to delimit or delete the record and it runs error free both time log and payroll log.
Regarding the employee master data , run the reports data inconsistency reports .
Regarding work center - check the validity of work center and assignments to the employee.
Regards
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Experts,
Can any one help me, how to change Info type 0009 record.
After change has been done, how to restrict it not effecting the retro ?
Please Suggest.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, I did not see that you have already run payroll for a couple of periods. As said earlier, the problem would be due to change in DOJ to a future date as compared to the wrong earlier date. The IT 1 that existed earlier on 1.10.2015 is not here any more.
It would not be possible to change this DOJ to a future date using PA40 or navigating to change of DOJ in PA30.
Following would be the alternatives:
1. Terminate the employee with the existing number.
1.1.1 Hire the employee with the correct DOJ and ref.pers.no = the wrong pers.no. This will help in copying the employee's infotypes like 2, 6, etc.
1.1.2 Enter any infotype data not copied.
1.1.3 Enter IT 2013 with any leave accrued with the wrong DOJ's per.nbr.
1.2.1 Terminate the emp. with the wrong DOJ. Ensure there is no term'n payment that is not applicable.
2. Continue with the per.nr with wrong DOJ,
2.1 For the period from the wrong DOJ to the day prior to the correct DOJ,
2.1.1 In IT 1: use a non-pay payroll area; change pos.no. as 9's.
2.1.2 In IT 7, IT 8: any change as required
2.2 Use IT 41 to indicate the correct DOJ.
2.3 If required (this may not be required due to above changes:
2.3.1 Enter any salary/tax adjustments - I'd think it would be to reduce salary paid with the wrong DOJ.
2.3.2 Change leave entl/accrual using IT 2013 - this would be to reduce.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Two employees have LOP before the New joining date.. when i am trying to delete the records. I am getting Error message like Infotype 0001 done not exist from before date ..
What should i do ? If i delete B2 results and run the time evaluation i wont get the error na ?
Please suggest . please give me some suggestions to resolve the issue.
For these 2 employees, try to restore the Hire Date (DOJ) and all Infotypes to the original DOJ Date, then Delete the LOP Absences. You should then be able to reset the DOJ Date to the corrected DOJ Date.
For all the concerned employees, since the new DOJ is after their original DOJ Date, you will have to modify their IT0003 so that Time Evaluation and Payroll Calculation is not allowed before their new DOJ Date. The reversal of Earnings and Deductions for the period prior to their new DOJ Date will have to be done manually.
Hi Remi,
thanks for the reply
For example : Employee Previous DOJ is 06.11.2015 Hire date changed to 16.11.2015
there is a LOP record in IT2001 from 06.11.2015 to 15.11.2015.
Now in the System All infotype records are changed to New hire date i.e 16.11.2015 Except IT0009.
You mean to say i need to change the hire date (IT0000 and 0001) to old hire date first i.e (06.11.2015)
and need to Delete the LOP records. After deleting the LOP records i need to change the Hire date latest (16.11.2015)
Please Confirm.
I have one more query, For few of the Employees All infotypes are changed to Latest Records Except IT0009. should i need to Delete the IT0009 or change or create the New record from 16.11.2015 .
Please Confirm.
If you have changed DOJ to a later date, after running time eval with the wrong DOJ, then this problem could occur.
To resolve this, delete time eval results (and pay results if you have run payroll).
Correct IT 3 so that it does not reflect any dates corresponding to the incorrect DOJ.
Then run time eval & pay roll.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sekhar,
Did you changed employee's date of joining after time evaluation run and payroll run?
This is generally coming due to DOJ changes after live time evaluation run along with live payroll run.
Check once.
Regards,
Sankarsan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.