Hi Gurus,
When ever we run PPDS Shelf life planning run we see that some order are not pegging at all.
If the req qty is today and receipt is created for tomorrow still a new requirement is created after the planning time fence.
When we run normal heuristics it works perfectly fine. Issue is happening only if we select Shelf life planning.
Please find the example below. When i use 00_002 works perfectly fine. We get issue only when we run shelf life heuristic .
Please suggest.
Thanks a lot in advance.
Regards,
Rajesh
Hi Kumar,
First you create the pegging and then you apply the Shelf life!
Thanks,
Regards Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rajesh,
As per my understanding the receipt elements are not considered by the order, So. create a Manual order in your product view and try to trigger the Product heuristic. If the batches are assigned to it, there is no inconsistencies in the order. If the batches are not considered. Recheck the status of the batch in OLTP system like MSC3N and see whether there are any changes.
Hope this clue would help you in understanding the issue. Rewards are highly appreciated.
Regards
Arvind Pabba
Hi Gurus,
It will be helpful if anyone can suggest .
Thanks & Regards,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.