Dependent requirement is planning for phantom item

former_member328966
Participant
0 Kudos

Hi

I am having one problem , the material is marked with phantom item - 50 but still it is creating dependent requirement.BOM level also it is marked with phantom

And procurement type used - E

Replicated the scenario in quality but it is working fine.

Accepted Solutions (1)

Accepted Solutions (1)

former_member328966
Participant

issue resolved by myself.

Thanks for the support

Answers (5)

Answers (5)

former_member328966
Participant
0 Kudos

Hi Solomon,

There is no stock available for the material. and reservation is also zero only.

former_member328966
Participant
0 Kudos

Hi Brahmankar,

The bom is available for phantom item.

solomon_macwan
Active Contributor
0 Kudos

hi Vishnu,

do you mean that reservation is getting generated for phantom material? if this is the case then check whether is has stock or not, if this is the case then remove the stock.

it will work fine.

regards,

Solomon

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Dependent requirements of superior assemblies should be passed on to the components of the phantom assembly directly. If no bill of material is created for the phantom, the logic summary cannot be executed and, as a result, the phantom is dealt with as a standard stock material.

Do you have BOM for phantom item?

Best Regards,

R.Brahmankar

ameya_beri
Active Contributor
0 Kudos

Hello Vishnu,

Please refer SAP help,

"If it is necessary, in individual cases, to create dependent requirements and procurement proposals for the phantom assembly during the planning of a material, you can override the Phantom assemblyattribute in the BOM. Enter an appropriate indicator for the explosion type in the item screen of the BOM. You maintain the explosion type in Customizing for MRP in the IMG activity Item data"


BOM Explosion with Phantom Assemblies - Material Requirements Planning (PP-MRP) - SAP Library

Check the phantom assembly BOM item in the BOM in quality and production system and confirm.

Best Regards,

Ameya B.