Hi All I was wondering can you tell me what the difference is in the 2 transactions.
I have also found only one order where the requirement quantity does not match what is in the BOM. This order has process order splits so do you know if this could affect it?
Hi,
There is no difference between these two transactions and they both call the same program RMCF0600.
However, MCRE is assigned in PP module and MCRX is assigned in PP-PI module.
Hope this clarifies your doubt.
Regards,
Ayoub.