does tolerance in maintenance plan affect required start/ end date in notification?

0 Kudos
  1. Hi...

i have created a maintenance plan with monthly strategy.. refer below image for same

  1. scheduling....

SCHEDULING OVERVIEW

NOTIFICATION IN DISPLAY MODE

MY QUESTION IS .... does tolerance given in maintenance plan affects  required start date/ end date in notification????

Accepted Solutions (0)

Answers (3)

Answers (3)

pardhreddyc
Active Contributor
0 Kudos

Dear,

Tolerance defines the period within which late or early completion impacts subsequent scheduling of Plan.

Tolerance is set for late completion and (–) Tolerance for early completion.

If completion is within Tolerance period it is not considered late or early and does not impact schedule.

If completion is out-with Tolerance period it will impact schedule taking account of Shift Factor values.

Example for 30 day cycle :

                    Plan date                           Plan date                        Plan Date

The Shift Factor applies in event of late or early completion of Maintenance Task (Call Object).

It defines how much subsequent schedule dates will be changes as result of later or early completion.

Regards,

Pardhu

Former Member
0 Kudos

Hi Rahul,

Tolerance along with Shift Factor decides the next planned date. If the variance between actual completion and planned date of the previous call was outside the tolerance, the next planned date will be decided based on shift factor defined.

For your case, shift factors are 0. So no effect even if Tolerance is defined.

Tolerance - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library

Shift Factor - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library

Also read F1 help of Tolerance field...


MTerence
Active Contributor
0 Kudos

Hi Rahul,

For 1 Month (30 days) and 10% Tolerance

So the tolerance is 3 days.

If the completion is made no more than 3 days before the planned date, then there wont be any tolerance applicable, no change of dates. In case if it is above 3 days, then system will change the days of scheduling accordingly

In your case, you need to complete the Notification 3 days beyond the actual planned date, then you will get the difference.

Regards

Terence