MM Purchase Order Advance paid

Former Member
0 Kudos

Hi,

      My scenario is first we create purchase order then release same order no and make advance payment via f-48 and advance document is post.

In purchase order history tab generate in purchase order.

      My requirement is if the purchase order history tab is generate system should not allow to change PO Qty and rate in purchase order.

Amit G

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member183379
Contributor
0 Kudos

Dear Amit,

Look like you need to go with development for the same.

Use EKBE for advance payment reference and block Po for changes with the help of Abaper.

Refer the following -

https://scn.sap.com/thread/2083910

Reg,

Bhg

Former Member
0 Kudos

Hi

Think Of it, keep the advance part separate. You can introduce release strategy(for release & re-release) for your PO to control the changes . Once your PO is released then Advance request can be raised against the PO.

BR

Sam